BARDON HILL QUARRY – 2018-2019
Dawnus Construction Limited
Project - Bardon Hill Quarry – Fuelling Area - February – March 2018 - A new fuelling area for the quarry plant which consisted of bases and roadways built using mesh reinforcement and concrete to construct.
Project - Bardon Hill Quarry – Crusher Building - April 2018 – January 2019 – A 28 metre high structure consisting of bases, walls and plinths to form the crusher building with 15,000 cubic metres of mass fill concrete poured between the quarry rock face and the building.
Project - Bardon Hill Quarry – Radial stacker and other miscellaneous works – August 2019 – October 2019 - A semi-circular base and wall structure for the bulk storage of aggregate delivered by conveyor from the crusher house.